The General Direction of Roads has begun this week the works of arrangement and conditioning of the section of the highway C-7 of La Huerta, at the height of the Cross of the Mission, on the outskirts of the urban area, which recorded material damages to As a consequence of the rainy season in December and that forced to cut a section of the way for several weeks.
In January, the General Direction of Roads processed the contracting of the works in order to respond to a problem that has been dragging since the end of last December.
The works, which are being carried out by the commercial "José Díaz García, SA", have a budget of 85,882.06 euros and have a period of execution of a month and a half, during which time this route will be cut to traffic.
This fact will force the C-7 road of La Huerta to be cut off to traffic during the period of time the actions in its communication with the urban center, which will lead to the use of alternative routes by El Rulo and El Cañico, among others.
The municipal government had repeatedly requested the General Directorate of Highways for the beginning of the works in order to end the discomfort that the state of this road caused to users and neighbors of the area.
Source: Ayuntamiento de Totana